Oil Refining
--------------------------
Oil Trading
--------------------------
Leasing & Storage
--------------------------
Grease Manufacturing
--------------------------
Fujairah Oil Terminal
Contact :
-----------------------------------
connect@gulfpetrochem.com
 
About Oil Storage Terminal
  • Independent oil storage terminal.
  • Approx 200,000 m2 land adjacent to the Khorfakkan highway and close to Port of Fujairah.
  • Project Consultants for Engineering, Procurement & Construction Management - Mott MacDonald.
  • Project to be executed in phased manner with a Master Plan for over 1 million cubic meters.


Phase I Plan
Phase 1 Plan has a total capacity of 425,000m3 for Class 3 products and is scheduled for completion in mid-2011.
  • Total capacity of 425,000m3 for Class 3 products with 17 tanks.
    (ranging from approx 14,000m3 to 40,000m3).
  • Fuel Oil (with heating & blending provisions), Gas Oil and Cutter Stocks.
  • Connected by dedicated piping to Port of Fujairah Matrix Manifold for onward guaranteed connectivity to any of 9 berths on OT-1&2 .
  • Piggable berth pipelines for complete product recovery.
  • Berth pipeline flow rates of 3,000m3/hr.
  • Simultaneous operations for Fuel Oil and Gas Oil:
    • Import or export
    • Inter Tank Transfers
    • Blending
    • Road Tanker dispatches through productwise dedicated truck gantry
  • All tanks, structures and facilities designed in accordance with international standards and complying with local regulatory rules – API 650, NFPA 30, NFPA 70, etc.
  • Emphasis on Environment, Safety and Health for both Design and operations.
    • Tank spacing, Fire Fighting, electrical zone classification, escape routes for safe evacuation as per standards.
    • HDPE liner for bulk storage area, Oil Water Separator for drainage system, concrete flooring for spill prone areas etc.
    • Safety Showers, safe operating platforms, safety barriers & guards for machinery etc provided.
  • Central Control Room with SCADA system for remote terminal operations.
  • All utilities like hot oil heaters, laboratory and workshop.


Phase II Plan
Phase II plan has been planned for a capacity of 600,000m3 to include provision for Class 1 and 2 products as well.
  • Provision for
    • Class 1 products like Gasoline, Naphtha
    • Class 2 products like Jet A1
    • Class 3 products like Fuel Oil, Gas Oil
  • Envisaged Facilities
    • Storage tanks with Internal Floating Roofs for Class 1 & 2 products
    • Gasoline blending provisions
    • Additional berth pipelines and pumps for new products provision made in Phase 1
    • Dedicated facilities for Jet A1 storage and handling
Privacy Policy | Copyright © 2009 GulfPetrochem . All rights reserved. Powered by M&A Associates